Compliance Requirements
                                          
The following is a summary of the requirements described throughout site.  As you can see there are
numerous things that have to occur prior to the job starting, on a daily, weekly, monthly and yearly basis.  
This list is not a comprehensive list of all items that are required, however they will get you through the
major items that can delay a project.  Use this list as a base to add other items as they become evident.  
Learn from each project and keep the list with you.  Don’t rely on your memory.

Initial Compliance Items
  • Confirm a Notice of Award has been issued has been issued by the owner
  • Confirm a Notice to Proceed has been issued by the owner
  • Procure Insurance for the Prime Contract
  • Procure Bonds for the Prime Contract
  • Confirm the Prime contract has been fully executed
  • Review the Prime Contract
  • Review all subcontractor contracts
  • Obtain and review a copy of the bids and scope letters of the low subcontractor bids
  • Confirm subcontracts have been send to the subcontractors for signature
  • Monitor to confirm when subcontracts have been fully executed
  • Procure required Subcontractor Bonds
  • Confirm receipt of initial insurance from subcontractors
  • Create a schedule of values
  • Conduct an in house Pre Job Review to discuss any special items in the contract or subcontracts
  • Distribute all contract documents to subcontractors and suppliers
  • Confirm Accounting Interface with the Estimate has been completed for budget reporting
  • Review Initial budget reports to confirm they match the Prime Contract amount and individual
    subcontract amounts
  • Conduct a Pre-Construction Meeting
  • Administration Manual
  • Location
  • Send out Invitations
  • Confirm attendees prior to the meeting
  • Create CPM Schedule
  • Review the CPM Schedule Review prior to submission to the architect and subcontractors

Jobsite Items
  • Billings Notification letters
  • Safety Notification letters
  • MSDS Notification letters
  • Certified Payroll Notification letters
  • Record Drawings Notification letters
  • Post all required OSHA and Labor Postings at Job Office
  • Create and Post an Emergency Action Plan per OSHA requirements
  • Confirm or create a Storm Water Pollution Prevention Plan
  • Set up files from standard list
  • Confirm there is Job Specific Illness and Injury Prevention Plan at the jobsite office
  • Confirm there is a company safety program at the jobsite office
  • Confirm there are fire extinguishers for the jobsite office
  • Confirm there is a first aid kit and other required medical items at the jobsite office
  • Obtain MSDS Sheets from Each contractor
  • Procure all supplies and furnishings
  • Determine a priority list of contracts and submittals
  • Set up temporary utilities
  • Telephone
  • Power
  • Water
  • Toilets
  • Trailers
  • Acquire all required Permits
  • Verify Requirements with architect for project closeout information and record drawings
  • Create a Submittal Register
  • Send submittal register to architect to review requirements
  • Call subcontractors to convey submittal requirements
  • Confirm all Substitution Requests are submitted by the subcontractors by the date noted in the
    contract documents
  • Submittals Notification letters
  • Set Up Record Documents Set


Daily Compliance Items
  • Schedule status – Review the project and note start and finish dates of activities on the record
    schedule
  • Safety Review – Review the project for safety items per the safety program and OSHA guidelines
  • Submittal Status – Review the log for items to be returned and submitted that are due and that
    are critical to the project schedule.
  • PCO Status - Review the log for items to be returned and submitted that are due and that are
    critical to the project schedule.
  • RFI Status - Review the log for items to be returned and submitted that are due and that are
    critical to the project schedule.
  • Process Invoices – General invoices should be processed as quickly as possible to insure
    timely payment and integration into costing reports
  • Receive Subcontractor Daily Reports – Confirm all reports are received each day
  • Harris Daily Reports – Confirm the superintendent has completed the daily report and it matches
    the reports submitted from the subcontractors.
  • Time sheets – Confirm timesheets are completed and entered or sent to the accounting
    department
  • Review record drawings for items to be covered – Review the project to determine what will be
    covered and confirm that the record drawings have been updated prior to the areas being
    covered
  • Complete Storm Water Pollution Plan reports as required

Weekly Compliance Items
  • Jobsite Safety Meetings
  • Jobsite Coordination Meetings - Owner, Subcontractor and Pre-Installation Meetings
  • Obtain Record Drawings from Contractors as required.
  • Review Certified Payroll for compliance
  • Take Progress Photographs
  • Post Record Documents

Print and Distribute at the jobsite to the Superintendent and/or Project Manager
  • RFI Log
  • Costs Logs
  • Submittal Logs

Monthly Compliance Items
  • Complete and send Operations Report to Corporate office
  • Send Photographs to Corporate Office
  • Receive and process Subcontractor Progress billings
  • Process Owner Progress Billings
  • Review and Reconcile Variable Cost Log with Job Cost Detail
  • Update Schedule and send update form to the Scheduling Department
  • Review status of insurance and notify contractors of pending expirations
  • Finalize all outstanding change order requests by the end of each month.

Yearly Compliance Items
  • Post Company Safety Form in month of February
  • Finalize all invoices for last month of previous year no later than January 15th of the following
    year.

Project Completion Compliance Items
  • Receive verification from all contractors that all costs have been submitted
  • Finalize all outstanding costs from suppliers and subcontractors
  • Complete all Punchlist items
  • File Notice of Completion
  • Process final progress billings
  • Compile and Submit Closeout Documents
Disclaimer: All information provided on constructionreference.com is provided for information purposes only. The information included is not intended as
legal advice and does not represent advice with regard to specific practices or undertakings and construction reference.com shall not be responsible for any
damages of any kind including direct, indirect, incidental, special or consequential damages that may arise out of or result from reliance on the information
provided on this web site.